Thai cement plant installs ThyssenKrupp Polysius' Prepol SC alternative fuels system
19 January 2023Thailand: ThyssenKrupp Polysius says that it has successfully supplied and installed a Prepol SC alternative fuels (AF) system at a 12Mt/yr cement plant in Thailand. The system will supply the plant's four lines with 4000t/day of AF.
ThyssenKrupp Polysius' Asia Pacific CEO Lukas Schoeneck said "Asia Pacific, with its tremendous municipal solid waste (MSW) problem, is ideal when it comes to replacing coal with AF. The Prepol SC technology significantly reduces the need to treat MSW before using the inherent calorific value. Additionally, it helps to further reduce the ambitious CO2 limit targets in the region."
ThyssenKrupp Polysius Asia Pacific to supply step combuster for cement plant in South Korea
10 August 2022South Korea: ThyssenKrupp Polysius’ Asia Pacific division has won an order to supply a Prepol SC type step combustion chamber for an unnamed cement plant in South Korea. The scope of the contract includes engineering, mechanical equipment and some modifications to the preheater tower. The commissioning of the system is planned for the end of 2023.
Regional chief executive officer Lukas Schoeneck said “The current turbulence on the coal market create a lot of pressure in cement plants to significantly increase the efforts on alternative fuels. Especially when talking high thermal substitution rates and lower quality alternative fuels, combustion chamber technologies connected to the calciner – like the Prepol SC - are the most suitable solution in the cement industry. Congratulations to the colleagues in Germany and in Asia working on this project.”
ThyssenKrupp to upgrade Ciments Calcia’s Airvault cement plant
07 December 2021France: Germany-based ThyssenKrupp has won a contract for the installation of a new 4000t/day clinker line at Ciments Calcia’s Airvault cement plant in Poitou-Charentes. The supplier expects the new line to double the plant’s clinker capacity while also reducing its CO2 emissions. It is intended to replace the two existing lines at the site.
ThyssenKrupp will supply a 1200t/hr double-shaft hammer crusher, a longitudinal blending bed, a 370t/hr Quadropol QMR² 45/23 type vertical roller mill and a 10,000t tangential blending silo to process raw materials for the line. A single-string, five-stage Dopol type cyclone preheater with integral calciner will be supplied that is suitable to use with alternative fuels, with the possibility of conversion to oxyfuel in future. ThyssenKrupp plans to preassemble the preheater, reducing anticipated construction time ‘by several months.’ The plant also includes a Polytrack clinker cooler, a solid recovered fuel (SRF) preparation line and dedusting systems. Commissioning is scheduled for mid-2024.
No value for the project has been disclosed by Ciments Calcia or ThyssenKrupp. However, Ciments Calcia previously announced a proposed investment of Euro300m in January 2021.